Tuesday August 14, 2012

 

Congratulations to BCC Engineering, Inc. who has been selected by FDOT District 5 to design the new St. Johns Heritage Parkway Interchange & I-95 Project.  Design work will begin in November 2012 and is estimated to take approximately 20 months.

 

 NEWS BULLETIN: FUNDING APPROVED FOR I-95 INTERCHANGE AT St. JOHNS HERITAGE PARKWAY.

Design  $3,065,190 - Construction $30,728,643

       Work will begin October 2012 and estimated to be finalized by July 2013.

UPDATED SCHEDULE FOR I-95 AND PARKWAY CONSTRUCTION
AS OF JULY 2012:

-        Palm Bay Interchange Project PD&E Study Approval Hearing est. December 2012.

-        Interstate 95 and St. Johns Heritage Parkway Location Design Federal Highway Approval est. July 2013.

-        Design-Build Contract advertised est. August 5, 2014.

-        Open Bids for Design-Build contract est. February 25, 2015.